Wednesday, May 22, 2013

Certification Questions from Syllabus


  • Which procurement process(es) normally end with the goods receipt and not with the invoice date?
  1. Procurement from another plant in the company using a stock transfer order
  2. Stock transfer of materials by means of subcontracting
  3. Normal purchase of materials from a vendor without provision of components
  4. Procurement of material by means of consignment 
Ans: 1,4


  • A plant can be assigned to several company codes.
  1. True
  2. False
Ans. False
  • A purchasing organization can act for several plants
  1. True
  2. False
Ans. True
  • A purchasing group must always be assigned to a purchasing organization
  1. True
  2. False
Ans. False
  • A purchasing organization must always be assigned to a company
  1. True
  2. False
Ans. False
  • You can create a purchase order with reference to a purchase requisition
  1. True
  2. False
Ans. True
  • Which organization levels do you have to indicate when entering a purchase order?
  1. Client
  2. Company Code
  3. Plant
  4. Storage Location
  5. Purchasing Organization
  6. Purchasing group
Ans. 2, 3, 5,6

  • What are the effects of the entry of goods receipt against a purchase order in the SAP system?
  1. The PO is deleted
  2. An accounting document can be generated
  3. A material document is created for each item
  4. The PO history is updated for each item of the PO.
  5. A material document is generated
Ans.2,4, 5
  • Which of the following can you enter using the transaction MIRO?
  1. Subsequent delivery
  2. Subsequent debit
  3. Invoice
  4. Subsequent adjustment
  5. Credit Memo
Ans.2, 3,5

No comments: